Construction of the nuclear power plant in the Republic of Belarus. Output of power and connection with the power system

  • The main electrical circuit of the electrical switchgear and connection with the power system.
  • Blocks No. 1 and No. 2. Development of working documentation for a complex of emergency control systems for nuclear power plants.

Customer: JSC ASE Engineering Company

  • 330 kV substations Postavy, Smorgon and 7 outgoing 330 kV high voltage lines.

Customer: RUE Grodnoenergo

General contractor: LLC North China Power Engineering and Design Company affiliated with the Chinese Energy Engineering Consulting Corporation (NCPE)

Wind energy park. Construction in village Grabniki of Novogrudok district.

Customer: RUE Grodnoenergo

Reconstruction of 750 kV substation Belorusskaya.

Customers: RUE Minskenergo, RIKO, d.o.o.

Petrikov Ore Mining and Processing Complex. Construction of 330/110/10 kV substation Petrikov.

Customer: OJSC Belgorkhimprom

Construction of 110 kV substation Staroborisovskaya with 110 kV cable lines in Minsk. 1st and 2nd stages.

Customer: RIKO, d.o.o.

Construction of 110 kV cable lines CHP-3 – 110/10 kV substation Podlesnaya.

Customers: RUE Minskenergo, RIKO, d.o.o.

Reconstruction of 330/110/10 kV substation Minsk-Severnaya with 110 kV power transition lines of Minsk district, Minsk region.

Customer: LLC North China Power Engineering and Design company affiliated with the Chinese Energy Engineering Consulting Corporation (NCPE)

Digital substation 330 kV Metallurgicheskaya

Customer: RUE Gomelenergo

Chinese-Belarusian Industrial Park. Internal engineering and transport infrastructure. The first stage of the construction. 110 kV substation Technopark.

Customer: China Machinery Engineering Corporation (CMEC)

Construction of a mining and processing plant with a capacity of 1.1 to 2.0 million tons of potassium chloride per year at Nezhinsky raw material base (eastern part) of the Starobinsky potassium deposit section. Construction of the 110 kV Nezhinskaya substation with a 110 kV overhead line Kaliynaya – Nezhinskaya.

Customer: foreign LLC Slavkaliy, LLC PassatProekt

Wind power plant Asmolovichi and Solar power plant Asmolovichi.

Customer: CJSC REAG Mogilev

OJSC Belarusian Metallurgy Plant – managing company of holding Belarusian Metallurgy Complex. Organization of the production of rolled steel with the construction of a wire-rod mill. External power supply. 330 kV, 110 kV substations.

Customer: RUE Gomelenergo

Photovoltaic electrical station Gelios, 55 MW

Customer: Belorusneft (Production Union)

We look forward to working with you!

Contacts

220037, Republic of Belarus,

Minsk, 1st Tverdy lane, 5

Contact phone numbers:

+375 17 388-99-00

+375 17 388-99-10 (fax)